LNG refueling station construction process

  • 分类: 公司新闻
  • 作者: admin
  • 来源:
  • 发布时间:2023-04-16
  • 访问量: 589

【概要描述】Part 1: General Process of Gas Station ConstructionThe construction of natural gas refueling stations must be approved in accordance with relevant national construction regulations and procedures. The...

河北欧意诺燃气设备有限公司网站上线

【概要描述】Part 1: General Process of Gas Station ConstructionThe construction of natural gas refueling stations must be approved in accordance with relevant national construction regulations and procedures. The...

  • 分类: 公司新闻
  • 作者:admin
  • 来源:
  • 发布时间:2023-04-16
  • 访问量: 590
详情

Part 1: General Process of Gas Station Construction

The construction of natural gas refueling stations must be approved in accordance with relevant national construction regulations and procedures. The handling of preliminary procedures for gas stations is a prerequisite and necessary condition for the smooth implementation of gas station construction, as well as the foundation and guarantee for the handling of procedures for the later operation of gas stations.

Gas refueling stations are different from ordinary buildings, and their construction process requires strict review. After the construction is completed and passes the initial inspection, they undergo acceptance from all aspects of the government and obtain opinions and certificates from relevant departments.

The preliminary procedures for the construction of gas stations include project feasibility study report (or project proposal), project approval document (National Development and Reform Commission), construction land approval letter, state-owned land use certificate (National Land and Resources Bureau), topographic survey map (with vectorized CD, surveying unit), planning red line (Planning Bureau), geological survey report (surveying unit), construction drawing design (design unit), planning permit (Planning Bureau) Construction drawing review opinions (Municipal Construction Commission Drawing Review Office), construction project Construction permit (Municipal Construction Commission), construction project fire protection design review opinions (Fire Bureau), safety assessment report approval (Work Safety Supervision and Administration Bureau), environmental assessment report approval (Environmental Protection Bureau), pressure pipe installation safety quality supervision and inspection declaration form (Party A applies for technical supervision unit) Special equipment installation, renovation, and maintenance notice (after the construction unit applies for technical supervision, a copy shall be submitted to Party A for retention).

Post construction procedures for gas refueling stations: opinions on fire safety acceptance of construction projects (fire bureau), hazardous chemical business license (safety production supervision and management bureau), quality supervision and inspection report of pressure vessel products (quality and safety inspection research institute of boilers and pressure vessels in the autonomous region), business license (industrial and commercial bureau), enterprise organization code certificate (quality and technical supervision bureau of the autonomous region) Inspection Report on Lightning Protection and Static Electricity Prevention Facilities (Autonomous Region Product Quality Supervision and Inspection Institute), Pressure Vessel Use Certificate, Gas Cylinder Filling Certificate (Autonomous Region Quality and Technical Supervision Bureau), Property Certificate, etc.


1、 Site selection


(1) The construction unit is familiar with the policies and standards for station construction. In the urban area or on the main transportation road, it should be close to water, electricity, and gas sources, close to vehicle sources, convenient for gas refueling, and basically meet the fire protection, environmental protection, and safety requirements in urban planning and standards. Therefore, the initial site for station construction is selected;

(2) The competent department, construction, planning, safety supervision, fire protection, environmental protection, and design shall be designated on site.

(3) Handling land acquisition procedures and land certificates in the national land department:

(4) Apply for planning land permit and construction land permit in the planning department.


2、 Project approval

(1) The construction unit submits a station construction application to the local industrial production management department (National Development and Reform Commission);

(2) Provide corresponding materials: project proposal, feasibility study report, and site selection report;

(3) The industry regulatory department or the National Development and Reform Commission approves the project initiation.


3、 Design

(1) Before the preliminary design, the construction unit shall provide the design unit with information such as site topographic map, natural gas quality data, meteorological data, seismic data, water, electricity, gas source data, station scale, preliminary equipment selection, geological survey data, environmental impact assessment report, cultural relic survey data, etc.

(2) Preliminary design by the design unit: general layout; The architectural style and style of individual buildings (gas sheds, station buildings, etc.); Gas station rendering; Main equipment configuration; Total project cost; Preliminary design of water, electricity, and gas processes; Explain whether it meets national standards and urban planning; Whether the fire protection, environmental protection, safety, etc. of the gas station meet the standard requirements.

(3) Preliminary design review: The competent department, National Development and Reform Commission, construction, planning, fire protection, environmental protection, safety supervision, design, and owners participate in the review of the preliminary design;

(4) The competent department or construction department shall issue preliminary design review opinions;

(5) Construction drawing design: The design unit shall design the process, general layout, architecture, structure, electrical appliances, water supply and drainage, and HVAC of the gas station based on this, and prepare a construction blueprint.


4、 Application for construction

(1) Preliminary design report for fire protection and environmental protection review, issuance of approval opinions, and handling of safety three simultaneous certificates by safety supervision;

(2) Submit the preliminary general layout plan (including approval opinions on fire protection, environmental protection, and safety supervision) for planning review, conduct surveys, and draw red lines;

(3) Planning and obtaining engineering planning permits;

(4) Apply for Construction permit for construction;


5、 Construction

(1) Handle equipment, civil engineering, installation, water, electricity, gas engineering, supervision bidding, and sign contracts;

(2) Apply for a quality inspection authorization letter at the quality inspection station;

(3) Handling contract authentication during construction;

(4) Organize construction.


6、 Acceptance

(1) Conduct engineering quality inspection and issue quality inspection reports;

(2) Conduct individual inspections on fire protection, safety, environmental protection, pressure vessels, etc., and issue individual inspection reports, hazardous chemical safety evaluation reports, lightning and static protection testing reports, and environmental protection evaluation testing reports;

(3) Apply for a chemical hazardous material business license at the safety supervision department, a pressure vessel use license at the quality supervision bureau, and a filling registration certificate;

(4) The quality inspection department verifies and calibrates the gas dispenser, and issues a measurement and usage license;

(5) Employees shall receive technical training from relevant departments and obtain work permits;

(6) Trial operation, acceptance, rectification, and improvement;

(7) Before comprehensive acceptance: The construction unit prepares to apply for completion acceptance reports, relevant approval documents, design materials, construction materials, completion materials, quality inspection materials, supervision materials, material testing materials, financial settlement materials, management systems, emergency plans for accident handling, and other relevant materials.

(8) The competent department shall preside over the completion acceptance report, with the participation of the construction committee, planning, fire protection, environmental protection, safety office, quality supervision, experts, and design and construction units;

(9) Apply for a gas business license from the industry management department, a business license from the Public and Commercial Administration Bureau, and a gas station qualification certificate from the gas management department;

(10) Production and operation.


Part 2: List of Approval Processes for Gas Filling Stations

Steps, procedures, content, and approval by the approval authority require relevant materials, approval documents, or certificate names

1. City (County) Development and Reform Commission A, Project Application Form B, Project Proposal (Feasibility Study Report) A, Approval of Project Proposal B, Approval of XX Gas Co., Ltd

2. Approval of Enterprise Name: Regional Administration for Industry and Commerce A. Approval of Project Proposal/Feasibility Study Report B. Approval of XX Gas Co., Ltd. Approval of Name of XX Gas Co., Ltd

3. The Technical Supervision Bureau of the region where the organization code is located A, "Approval for Project Proposal/Feasibility Study Report" B, "Approval for XX Gas Co., Ltd." C, "Approval for Agreeing to the Name of XX Gas Co., Ltd.", and "Organization Code Certificate"

4. Local accounting firm A for capital verification, account opening bank, capital verification payment B, official seal "Capital Verification Report"

5. Business License Administration for Industry and Commerce A, Approval for the Name of XX Gas Co., Ltd. B, Organization Code Certificate C, Capital Verification Report Business License (Preparation Period)

6 Review opinions of the local and regional development and reform committees (red Header file document) of the feasibility report review audit committee A, the feasibility report B, the unit's application report for the review of the feasibility report

7. Determine Station Site A, Planning and Management Bureau (Planning Department of Construction Bureau) B, Public Security and Fire Protection Bureau A, "Land Red Line Map" B, "Station Area Design Map" A, "Construction Land Planning Permit" B, "Fire Approval Opinions"

Review of the preliminary design of the 8 station area (environmental impact assessment) by a qualified local environmental review unit, including "Preliminary Design Plan" A, "Environmental Impact Assessment Report" B, and "Preliminary Design Plan Approval Form"

9. Safety Supervision Review Local or Regional Safety Supervision Bureau A, "Station Area Design Drawing" B, "Safety Supervision Review Report", "Safety Assessment Approval or Opinion"

10. Planning Department of the Local Construction Commission for Construction Land A, "Approval for Project Approval" B, "Station Area Planning Plan" C, "Address Exploration Report" and "Construction Engineering Planning Permit" by the Exploration and Design Institute

11 Land Acquisition and Resources Bureau A, "Business License" B, "Construction Land Permit" A, "Land Transfer Contract" B, "State owned Land Use Certificate"

12 Bank account opening XX Bank A, "Business License" B, "Organization Code Certificate" C, "Capital Verification Report" D, Official Seal E, Reserved Seal "Basic Account Opening Permit"

13 Statistical Registration Bureau A, Organization Code Certificate B, Business License, Statistical Certificate

14. Planning and Management Bureau of Construction Engineering Planning License (Planning Department of Construction Bureau) A. "Land Red Line Map" B. Review Opinions on Station Construction Drawing and Construction Drawing Planning C. "Approval Form for Construction Engineering Planning" and "Construction Engineering Planning License"

15. Approval of Gas Project Construction: Gas Office of the Construction Committee A. Business License B. Other required documents: Gas Project Construction Approval Letter

16. Fire Design Approval Public Security Fire Bureau A, Development and Reform


Part 3: Notice on the Implementation of the Interim Measures for the Approval and Management of the Construction of Automotive Gas Filling Stations in Beijing


To all districts, counties, bureaus, headquarters, and relevant units:


In order to control air pollution, accelerate the development of gas vehicles, and ensure the safe and orderly construction of vehicle gas refueling stations, the following notice is hereby issued for the approval and management of the construction of vehicle gas refueling stations in our city. Please follow and implement it.

1、 The construction, renovation, and expansion of vehicle gas refueling stations within the administrative area of our city should follow the principles of safety first, reasonable layout, ensuring gas supply, and convenient refueling in accordance with the overall construction plan of vehicle gas refueling stations in our city.

2、 All newly built, renovated, or expanded vehicle gas refueling stations, regardless of their scale, shall be declared and approved by the competent department of the construction unit to the Municipal Planning Commission according to the basic construction requirements. The Municipal Planning Commission shall, based on the application materials, jointly approve it with relevant departments such as the Municipal Administration Commission, Planning Bureau, Environmental Protection Bureau, and Fire Bureau.

3、 The construction of vehicle gas refueling stations should comply with the technical specifications and policy regulations of departments such as transportation, environmental protection, technical supervision, labor, fire protection, and public utilities. The completed vehicle gas refueling station must undergo acceptance by relevant departments such as fire protection, labor, technical supervision, and public utilities before it can be put into operation.

4、 Before handling the industrial and commercial registration procedures, the operating unit should obtain the qualification recognition from the gas industry management department and apply for the "Gas Station Operation License".

5、 The construction and management of vehicle gas refueling stations shall comply with the "Regulations on Urban Gas Safety Management", "Urban Gas Management Measures", and "Regulations on Qualification Management of Urban Gas Enterprises" jointly issued by relevant departments of the State Council, and shall also refer to the relevant construction and management regulations of gasoline refueling stations.

1.1 After the construction of the gas station is completed, the necessary construction procedures are as follows:

1. Preliminary procedures:

Project feasibility study report (or project proposal), project approval document (Planning Commission), construction land approval letter, state-owned land use certificate (Land and Resources Bureau), topographic survey map (with vectorized CD, surveying and mapping unit), planning red line (Planning Bureau), geological survey report (surveying unit), construction drawing design (design unit), planning permit (Planning Bureau), construction drawing review opinion letter (Municipal Construction Commission Drawing Review Office) Construction permit for construction projects (municipal construction commission), review opinions on fire protection design of construction projects (fire bureau), reply to safety assessment report (work safety supervision and administration bureau), reply to environmental assessment report (environmental protection bureau) Application Form for Safety and Quality Supervision and Inspection of Pressure Pipeline Installation (Party A applies for technical supervision unit) Special Equipment Installation, Transformation and Maintenance Notice (after the construction unit applies for technical supervision unit, submit one copy to Party A for retention).

2. Post stage procedures: Opinions on Fire Inspection and Acceptance of Construction Projects (Fire Department) Hazardous Chemical Business License (Work Safety Supervision and Administration Bureau) Pressure Vessel Product Quality Supervision and Inspection Report (Autonomous Region Boiler and Pressure Vessel Quality and Safety Inspection Institute) Business License (Industry and Commerce Bureau) Enterprise Organization Code Certificate (Autonomous Region Quality and Technical Supervision Bureau) Lightning Protection and Static Electricity Facility Inspection Report (Autonomous Region Product Quality Supervision and Inspection Institute) Pressure Vessel Use Certificate Gas Cylinder Filling Certificate (Autonomous Region Quality and Technical Supervision Bureau) Property Certificate